Latest pics of new Parliament out; Construction nearing final phase

Date:

New Delhi: The central government has released pictures of the new Parliament building. The photos of the interiors were released by the Union Ministry of Housing and Urban Affairs, which is responsible for the construction of Parliament and the reconstruction of the central vista.

Earlier it was said by November the construction will be complete, however, the works could not be completed on time. The officials are now saying that the work will be completed by the end of January.

In 2020, Tata Group took up construction for a contract of 861 crores. However, there are reports that the cost has gone up to 1200 crores.

It is reported that the main reason for the increase in expense is the increase in GST from 12 to 18 %.

The building was designed by Ahmedabad-based HCP Design. The construction work started in 2021.

The new Lok Sabha chamber has 888 seats. The Rajya Sabha chamber has 384 seats.

Related articles

India on High Alert: Widespread Monsoon Rains, Flood Warnings Issued for August 22, 2025

India is grappling with intense monsoon activity today, as heavy rainfall triggers flood alerts, particularly along the mighty...

China’s Fireworks: Where They Come From and Their Impact on the Environment and Health

Ah, fireworks—the loud, colorful phenomenon that we all collectively agreed upon should be part of every celebration, no...

India Braces for Mixed Weather Conditions As Rains Continue, Disrupting Daily Life in Several Regions – 21 August 2025

Weather Conditions Across India – 21 August 2025 In hindi भारत भर में मौसम की स्थिति – 21 अगस्त 2025 Also...

The U.S. Rejection of the IMO “Net-Zero Framework” Proposal

On August 12, 2025, the United States determined not to back the International Maritime Organization’s (IMO) Net-Zero Framework...